Power may be interrupted at any time during the scheduled period. Power may be restored earlier than scheduled. Therefore, please consider our lines and equipment energized at all times and take all necessary precautions.

Date Day Time Duration Areas affected Purpose
October 13, 2018 Sat 8:00 am – 12:00 nn 4 hr
San Fabian :  Portion of Mabilao (Consuelo Perez Compound)
Primary line revamp
11:00 am – 3:00 pm 4 hr
Manaoag:  Portion of Inamotan
October 12, 2018 Fri 8:30 am – 11:30 am 3 hr
Calasiao :  Portion of San Miguel (Sitio Parongking)
Primary line revamp
October 6, 2018 Sat 3:00 am – 3:40 am 10 min
Dagupan City:  Nueva St., Portion of Fernandez St., and Galvan St.
Primary line extension
8:20 am – 8:30 am 10 min
3:30 am – 5:30 am 2 hr
Dagupan City:  Portion of Mayombo (Insider), Perez Market Site, Rizal St. Extension, and Portion of Perez Blvd. (From corner Galvan St., to M.H. Del Pilar St.)
3:30 am – 8:30 am 5 hr
Dagupan City:  Herrero St., Nable St., and Portion of Pantal.
October 4, 2018 Thu 8:00 am ‐ 12:00 nn 4 hr
Sta. Barbara:  Portion of Balingueo (BLISS)
Primary line revamp
September 29, 2018 Sat 8:00 am ‐ 12:00 nn 4 hr
San Jacinto:  Portion of Macayug (Sitio Boquig)
Primary line revamp
September 8, 2018 Sat 6:30 am – 6:40 am 10 min
Calasiao:  Portion of Nalsian (Nalsian-Bacayao)
Dagupan City:  Portion of De Venecia Highway, Bacayao Sur, Lasip Grande, Pogo Grande, Lasip Chico, and portion of Lucao (Lucao-Arco)
Upgrading of insulation
10:20 am – 10:30 am 10 min
6:30 am – 10:30 am 4 hr
Dagupan City:  Malued
September 6, 2018 Thu 6:30 am – 7:00 am 30 min
Manaoag:  Portion of Babasit, portion of Poblacion (Soriano St., Tiong St., Aquino St., and Castro St.), Baritao, Pantal, San Ramon, and Mermer
Relocation of primary poles due to DPWH construction of Licsi bridge in Licsi, Manaoag
10:30 am – 11:00 am 30 min
6:30 am – 11:00 am 4.5 hr
Manaoag:  Licsi, Tebuel,Nalsian, Cabanbanan, Oraan East, Oraan West, Sta. Ines, Lelemaan, Inamotan, Baguinay, Matulong, and Parian
September 1, 2018 Sat 7:00 am – 7:30 am 30 min
Sta. Barbara:  Sonquil, Payas, Cablong, Carusucan, Patayak, and Balingueo
Primary line revamp
10:30 am – 11:00 am 30 min
7:00 am – 11:00 am 4 hr
Sta Barbara:  Sapang and portion of Maronong
August 30, 2018 Thu 12:00 nn – 5:00 pm 5 hr
Dagupan City:  Portion of Malued (Claveria-De Venecia road)
Primary line revamp
August 28, 2018 Tue 10:00 am – 2:00 pm 4 hr
San Jacinto:  Portion of Lobong (Sitio Mambog)
August 25, 2018 Sat 7:00 am – 7:10 am 10 min
Calasiao:  Buenlag and Songkoy
Upgrading of Insulation
10:50 am – 11:00 am 10 min
7:00 am – 11:00 am 4 hr
Calasiao:  Macabito
August 18, 2018 Sat 7:00 am – 8:00 am 1 hr
Calasiao:  Macabito
Upgrading of Insulation
11:00 am – 12:00 nn 1 hr
7:00 am – 12:00 nn 5 hr
Calasiao:  Buenlag and Songkoy
August 11, 2018 Sat 6:00 am – 10:00 am 4 hr
Calasiao:  Talibaew
Relocation of primary poles due to DPWH widening of Villamil bridge
9:00 pm – 10:00 am 1 hr
Calasiao:  Portion of San Miguel (Parongking and PNR Site) and Mancup
9:00 am – 11:00 am 2 hr
San Jacinto:  Portion of Labney (Sitio Inabaan)
Tree trimming
August 10, 2018 Fri 7:00 am – 7:30 am 30 min
San Jacinto:  All areas
Manaoag:  All areas
San Fabian:  All areas
Decommissioning and replacement of NGCP's 100MVA Power Transformer at San Manuel Substation. Shifting of power source of DECORP San Jacinto Substation and CENPELCO Mangaldan/Guilig Substation to NGCP's Balingueo Substation
August 4, 2018 Sat 8:00 am – 12:00 nn 4 hr
Dagupan City:  Portion of Bolosan (Bolosan Highway) and Mamalingling
Relocation of primary poles due to DPWH widening of Paldakit Bridge in Brgy. Bolosan
8:00 am – 12:00 nn 4 hr
Sta. Barbara:  Portion of Nilombot, Banzal, Erfe, and portion of Leet
Primary line revamp
August 2, 2018 Thu 5:30 pm – 6:00 pm 30 min
Dagupan City:  Brgy. I (Torres Bugallon), Brgy. II (Nueva), Brgy. IV (Zamora), Bonuan Binloc, Bonuan Boquig, Bonuan Gueset, Calmay, Carael, Herrero, Lomboy, portion of Lucao, Pantal, Poblacion Oeste, portion of Pogo Chico, Pugaro Suit, Salapingao, Tapuac, A.B. Fernandez Ave., Burgos St., Jovellanos St., Rivera St., Gomez St., Zamora St., Rizal St., Fernandez St., Galvan St., portion of Perez Blvd, and De Venecia Highway Extension
Emergency interruption due to damaged conductor caused by DPWH Contractor at Ramos Bridge, De Venecia Highway, Nalsian Calasiao
July 24, 2018 Tue 8:00 am – 12:00 nn 4 hr
Dagupan City:  Portion of Bolosan (Bolosan Highway) and Mamalingling
Relocation of primary poles due to DPWH widening of Paldakit Bridge in Brgy. Bolosan (Supersede the schedule interruption July 21, 2018)
July 21, 2018 Sat 6:00 am – 7:00 am 1 hr
Manaoag:  Calaocan, Lipit Norte, Lipit Sur, Pao, Poblacion, Pugaro, and Sapang
Relocation of primary pole at Baloking Bridge due to eroded soil base - Emergency Interruption
8:00 am – 9:00 am 1 hr
6:50 am – 7:00 am 10 min
Manaoag:  Baguinay, Baritao, Cabanbanan, Inamotan, Lelemaan, Licsi, Matulong, Mermer, Nalsian, Oraan East, Oraan West, Pantal, Parian, San Ramon, Sta. Ines, and Tebuel
7:50 am – 8:00 am 10 min
6:00 am – 9:00 am 3 hr
Manaoag:  Babasit, Bisal and Bucao
July 21, 2018 Sat 8:00 am – 12:00 nn 4 hr
Dagupan City:  Portion of Bolosan (Bolosan Highway) and Mamalingling
Relocation of primary poles due to DPWH widening of Paldakit Bridge in Brgy. Bolosan
8:00 am – 12:00 nn 4 hr
Sta. Barbara:  Portion of Nilombot, Banzal, Erfe, and portion of Leet
Primary line revamp
July 20, 2018 Fri 10:00 am – 3:00 pm 5 hr
Calasiao:  Portion of Nagsaing (Sitio Pagas)
Primary line revamp
July 13, 2018 Fri 6:00 am – 6:10 am 10 min
Calasiao:  Bued, Quesban and Gabon
Sta. Barbara:  Tuliao, Alibago, Malanay, Gueguesangen, Dalongue, Poblacion Sur, Poblacion Norte, portion of Maningding, Sapang, Maronong, Sonquil, Payas, Carusucan, Cablong, Patayak, and Balingueo
Primary line extension
11:50 am – 12:00 nn 10 min
8:00 am – 12:00 nn 6 hr
Calasiao:  Portion of San Miguel (from Calasiao Diversion Road Junction to Parongking Bridge) and Ambonao
10:00 am – 3:00 pm 5 hr
Manaoag:  Portion of Babasit (Babasit-Pugaro)
Primary line revamp
July 7, 2018 Sat 8:00 am – 12:00 nn 4 hr
Dagupan City:  Portion of Bonuan Gueset (Bagong Barrio)
Primary line revamp
July 5, 2018 Thu 8:00 am – 12:00 nn 4 hr
Calasiao:  Portion of Bued (Rusela Heights Subdivision)
Primary line extension
June 30, 2018 Sat 5:30 am – 6:00 am 30 min
Calasiao:  Portion of San Miguel (Kwik N Easy and Jollibee), portion of Nalsian (Chowking, Regency Hotel, PSA, and De Venecia Highway), portion of San Vicente, Dinalaoan, Ambuetel, Nagsaing, Malabago, Doyong, Buenlag, Songkoy, and Macabito
San Carlos City:  Cruz and Bolingit
Relocation of primary poles due to DPWH widening of Villamil Bridge
11:30 am – 12:00 nn 30 min
5:30 am – 12:00 nn 6.5 hr
Calasiao:  Poblacion East, Mabini St., (NLPDC, Calasiao Public Market, Fiesta Shopping Center, and Calasiao Municipal Hall), Lasip, Talibaew, and Mancup
June 23, 2018 Sat 7:00 am – 7:30 am 30 min
Dagupan City:  Portion of De Venecia Highway Extenstion, Portion of Arellano St., Bonuan Gueset, and portion of Bonuan Binloc
Primary line revamp
11:30 am – 12:00 nn 30 min
7:00 am – 11:00 am 4 hr
Dagupan City:  Portion of Bonuan Gueset (Bonuan Blue Beach Subdivision)
7:00 am – 12:00 nn 5 hr
Dagupan City:  Portion of Bonuan Gueset (Paras Road and Bonuan Tondaligan)
June 16, 2018 Sat 1:30 pm – 4:30 pm 3 hr
Calasiao:  Portion of Lasip (Sitio Otel)
Primary line extension
June 15, 2018 Fri 9:00 am – 4:30 pm 7.5 hr
San Fabian:  Portion of Binday and Colisao
Primary line revamp
June 15, 2018 Fri 8:00 am – 8:10 am 10 min
Dagupan City:  Portion of De Venecia Highway, Lasip Chico, Malued, and portion of Lucao (Arco)
Calasiao:  Portion of Mac Arthur Highway, portion of San Miguel, portion of Poblacion West, Nalsian, San Vicente, Banaoang, Dinalaoan, and Ambuetel
Primary line extension
9:50 am – 10:00 am 10 min
8:00 am – 10:00 am 2 hr
Dagupan City:  Bacayao Sur, Lasip Grande, and Pogo Grande
June 14, 2018 Fri 1:30 pm – 3:30 pm 2 hr
Manaoag:  Portion of Calaocan, Sapang, Pugaro, Pao, Lipit Sur, and Lipit Norte
Primary line extension
June 8, 2018 Fri 9:00 am – 12:00 nn 3 hr
San Jacinto:  Portion of San Jose
Primary line revamp
June 6, 2018 Wed 8:00 am – 8:30 am 30 min
San Jacinto: All areas
San Fabian: All areas
Manaoag:  All areas
Corrective maintenance by NGCP
5:30 pm – 6:00 pm 30 min
8:00 am – 4:00 pm 8 hr
Manaoag:  Portion of Cabanbanan, Lelemaan, Inamotan, Baguinay, Matulong, Parian, and portion of Mermer
Primary line revamp
June 2, 2018 Sat 9:00 am – 4:00 pm 7 hr
San Fabian:  Portion of Palapad (Eggcellent Breeding Farm)
Primary line revamp
June 1, 2018 Fri 7:00 am – 12:00 nn 5 hr
San Jacinto:  Portion of Lobong, Labney, Awal, and Bolo
Dagupan City:  Lomboy, Salapingao, and Pugaro Suit
Primary line revamp
8:00 am – 12:00 nn 4 hr
May 22, 2018 Tue 7:00 am – 7:30 am 30 min
San Fabian:  All areas
San Jacinto:  All areas
Manaoag:  All areas
Corrective maintenance by NGCP
9:00 am – 9:30 am 30 min
May 18, 2018 Fri 1:00 pm – 4:00 pm 3 hr
Manaoag:  Portion of Cabanbanan (Castillo St.) and Oraan East
Primary line extension
May 17, 2018 Thu 9:00 am – 11:30 am 2.5 hr
Sta. Barbara:  Portion of Minien East (Wedgewood Subdivision)
Replacement of rotten crossarm
May 12, 2018 Sat 6:00 am – 7:00 am 1 hr
Manaoag:  Galaban St., Aquino St., Baritao, Pantal, Tebuel, Licsi, Nalsian, Cabanbanan, Oraan East, Oraan West, Sta. Ines, Lelemaan, Inamotan, Baguinay, Matulong, and Parian
Relocation of primary poles due to DPWH widening of Baritao Bridge
10:00 am – 11:00 am 1 hr
6:00 am – 11:00 am 5 hr
Manaoag:  San Ramon and Mermer
May 4, 2018 Fri 1:30 pm – 4:30 pm 3 hr
Dagupan City:  Portion of Malued (fisheries)
Primary line extension
April 21, 2018 Sat 6:00 am – 6:10 am 10 min
San Fabian:  Anonang, portion of Angio, Aramal, Binday, Palapad, Colisao, portion of Ambalangan-Dalin, Erfe St., Alvear St., Rizal St., portion of Tempra-Guilig, Lekep-Butao, and Sevidal St.
Rerouting of lines due to DPWH bridge widening project at Cayanga, San Fabian
7:50 am – 8:00 am 10 min
6:00 am – 8:00 am 2 hr
San Fabian:  Real Highway, Caballero St., Cayanga, Sagud-Bahley, Nibaliw East, Nibaliw Vidal, Nibaliw Narvarte, Nibaliw Magliba, and Nibaliw Central
6:00 am – 10:30 am 4.5 hr
San Fabian:  Portion of Cayanga (from Saint Blaise School to Cayanga Bridge construction), Longos, Longos-Amangonan-Parac-Parac, and Longos Proper
April 17, 2018 Tue 6:00 am – 6:30 am 30 min
San Jacinto:  All areas
Manaoag:  All areas
San Fabian:  All areas
NGCP San Manuel Substation power transformer maintenance and correction of defects along San Manuel to San Jacinto transmission line
4:30 pm – 5:00 pm 30 min
April 12, 2018 Thu 10:00 am – 12:00 nn 2 hr
San Fabian:  Portion of Lipit-Tomeeng
Primary line extension
April 11, 2018 Wed 6:30 am – 6:45 am 15 min
Dagupan City:  Brgy. I (Torres Bugallon), Brgy. II (Nueva), Brgy. IV (Zamora), Bonuan Binloc, Bonuan Boquig, Bonuan Gueset, Calmay, Carael, Herrero, Lomboy, portion of Lucao, Pantal, Poblacion Oeste, portion of Pogo Chico, Pugaro Suit, Salapingao, Tapuac, A.B. Fernandez Ave., Burgos St., Jovellanos St., Rivera St., Gomez St., Zamora St., Rizal St., Fernandez St., Galvan St., portion of Perez Blvd., and De Venecia Highway Extension
Completion of rerouting of 69 KV line – Ramos Bridge widening at De Venecia Highway (DPWH project)
April 7, 2018 Sat 6:00 am – 11:00 am 5 hr
Dagupan City:  Rizal St. Extension
Primary line extension
10:00 am – 10:10 am 10 min
Dagupan City:  Mayombo-Highlander and Perez Market site
10:50 am – 11:00 am 10 min
10:00 am – 11:00 am 1 hr
Dagupan City:  Perez Blvd. (from corner Galvan St. to corner M.H. Del Pilar St.)
April 6, 2018 Fri 1:00 pm – 4:00 pm 3 hr
Sta. Barbara:  Portion of Patayak
Primary line extension
March 26, 2018 Mon 6:00 am – 6:30 am 30 min
Manaoag:  All areas
San Fabian:  All areas
San Jacinto:  All areas
Shutdown request by CENPELCO to facilitate the isolation of their Mangaldan Bari Substation for the preventive maintenance of the 5 MVA power transformer at the said substation due to severe oil leakage
March 24, 2018 Sat 5:00 am – 7:00 am 2 hr
Dagupan City:  Caranglaan, Bacayao Norte, portion of Mayombo, portion of M.H. Del Pilar St., and portion of Arellano St.
Primary line revamp
10:00am – 11:00 am 2 hr
5:00 am – 11:00 am 6 hr
Dagupan City:  Portion of MacArthur Highway (after Megasco-Caranglaan to Carmak-Mayombo), Pag-ibig Subdivision, Dona Margarita Subdivsion
March 20, 2018 Tue 8:00 am – 12:00 nn 4 hr
Dagupan City:  Portion of Malued (Gaudencio Siapno Road)
Primary line revamp
March 15, 2018 Thu 6:30 am – 6:45 am 15 min
Dagupan City:  Brgy. I (Torres Bugallon), Brgy. II (Nueva), Brgy. IV (Zamora), Bonuan Binloc, Bonuan Boquig, Bonuan Gueset, Calmay, Carael, Herrero, Lomboy, portion of Lucao, Pantal, Poblacion Oeste, portion of Pogo Chico, Pugaro Suit, Salapingao, Tapuac, A.B. Fernandez Ave., Burgos St., Jovellanos St., Rivera St., Gomez St., Zamora St., Rizal St., Fernandez St., Galvan St., portion of Perez Blvd., and De Venecia Highway Extension
Relocation of poles – Ramos Bridge widening at De Venecia Highway (DPWH project)
7:00 am – 10:00 am 3 hr
Calasiao:  Portion of De Venecia Highway (from PSA to corner Lasip Chico)
March 8, 2018 Thu 6:00 am – 12:00 nn 6 hr
San Fabian:  Portion of Mabilao, Lipit Tomeeng, Alacan, Tiblong, and Rabon
Upgrading of insulation
March 7, 2018 Wed 8:30 am – 12:00 nn 3.5 hr
Calasiao:  Portion of Poblacion East (Pandayan)
Primary line revamp
March 3, 2018 Sat 6:00 am – 6:10 am 10 min
Calasiao:  Portion of Bued, portion of Ambonao (Sitio Ambonao-Cruz), Cabilocaan
Sta. Barbara:  Tuliao, Alibago, Malanay, Gueguesangen, Poblacion Norte, Poblacion Sur, Dalongue, Maningding, Ventinilla, Primicias, Banaoang, Nilombot, Banzal, Erfe, Leet, Maticmatic, Tebag West, Tebag East, Botao, Minien West and Minien East
Upgrading of insulation
11:50 am – 12:00 nn 10 min
March 2, 2018 Fri 7:00 am – 12:00 nn 5 hr
Sta. Barbara:  Nilombot, Banzal, Erfe, and portion of Leet
Primary line revamp
February 28, 2018
Wed
8:30 am - 12:00 nn
3.5 hr
Dagupan City: Portion of Mayombo (Dona Margarita Subd. and PNR Site)
Primary line revamp

February 24, 2018
Sat
6:00 am - 7:00 am
1 hr
11:00 am - 12:00 nn
1 hr
San Fabian: All areas
6:00 am - 12:00 nn
6 hr
San Fabian: Cabaruan, and Portion of Angio
San Jacinto: Portion of San Vicente and Portion of Macayug
Upgrading of insulation

February 22, 2018
Thu
7:00 am - 7:10 am
10 min
11:50 am - 12:00 nn
10 min
San Fabian: Anonang, Osmena St., Erfe St., Rizal St., Alvear St., 
Sevidal St., Caballero St., Portion of Real Highway, Portion of 
Tempra-Guilig, Nibaliw East, Lekep-Butao, Cayanga, Sagud-Bahley,
Nibaliw Central, Nibaliw Magliba, Nibaliw Narvarte, Nibaliw Vidal,
Longos, Longos Proper, and Longos-Amangonan-Parac-Parac Fabrica
11:50 am - 12:00 nn
10 min
Dagupan City: Portion of Bonuan Boulevard and Portion of Bonuan Binloc
7:00 am - 12:00 nn
5 hr
San Fabian: Portion of Cabaruan, Angio, Aramal, Binday, Colisao,
Palapad, Ambalangan-Dalin
Upgrading of insulation

February 21, 2018
Wed
8:30 am - 12:00 nn
3.5 hr
Dagupan City: Portion of Bonuan Gueset (Camp 6, Paras Road)
Primary line revamp

February 17, 2018
Sat
1:00 pm - 5:00 pm
4 hr
Dagupan City: Portion of Mayombo (Dona Margarita Subd. and PNR Site)
Primary line revamp

February 16, 2018
Fri
7:00 am - 12:00 nn
5 hr
San Fabian: Nibaliw Vidal and Nibaliw Magliba
1:00 pm - 4:00 pm
3 hr
San Fabian: Portion of Alacan
Upgrading of insulation

February 15, 2018
Thu
8:00 am - 12:00 nn
4 hr
Dagupan City: Portion of Bonuan Gueset (Bonuan Blue Beach Subd.)
1:00 pm - 4:00 pm
3 hr
Dagupan City: Portion of Bonuan Binloc (Lateral road going BFAR)
Upgrading of insulation

February 10, 2018
Sat
7:00 - 12:00
5 hr
Calasiao: Portion of San Vicente, Dinaloan, Lumbang, and Ambuetel.
Primary line revamp

February 9, 2018
Fri
8:00am - 12:00
4 hr
Dagupan: Portion of Bonuan Gueset (Lateral road going to BJMP)
1:00 - 4:30 
3.5 hr
San Fabian: Portion of Nibaliw Narvarte (Sitio Sungyot and Holiday
baeach resort).
Upgrading of insulation

February 3, 2018
Sat
9:00 am - 12:00 nn
4 hr
Calasiao: Portion of Bued, Portion of Ambonao (Sitio Ambonao - Cruz),
and Cabilocaan
Primary line extension

January 26, 2018
Fri
7:00 am - 12:00 nn
5 hr
Manaoag: Portion of Poblacion (Llamido St. and Bautista St.),
Pugaro, Portion of Lipit Sur ( going to Lipit - Pugaro)
8:00 am - 12:00 nn
4 hr
Dagupan City: Lasip Chico
Primary line revamp

January 25, 2018
Thu
8:00 am - 12:00 nn
4 hr
San Fabian: Portion of Binday
Primary line extension

January 20, 2018
Sat
8:00 am - 12:00 nn
4 hr
Dagupan City: Portion of Bonuan Gueset (Ceralde St. going to
Bangusville)
8:00 am - 12:00 nn
4 hr
Dagupan City: Portion of Bonuan Gueset (Bonuan Tondaligan)
1:00 pm - 4:00 pm
3 hr
Dagupan City: Portion of Bonuan Binloc (Bonuan BLISS)
Insulation upgrading

January 13, 2018
Sat
8:00 am - 3:00 pm
7 hr
Dagupan City: Lomboy, Salapingao and Pugaro Suit
Primary line revamp

January 9, 2018
Tue
9:00 am - 12:00 nn
3 hr
San Fabian: Portion of Lipit-Tommeng